Safety Improvement Works : Junction of Pebblehill Road and Headley Common Road

Surrey County Council Highways contractors will be making adjustments to the Headley Common Road/Pebble Hill Road junction. The work involves altering the kerblines, islands, signage and road markings, priorities and undertaking carriageway resurfacing

A proportion of Headley Common Road will be closed throughout the construction phase – the southern ‘slip road’.

Headley Common Road will be closed in full to motorists between the Pebble Close and Pebble Hill Road junctions during the school Easter holidays (weeks commencing 3 April and 10 April)

Download a copy of the information leaflet being delivered to residents living near the junction.

Surrey Highways has published the following provisional works programme, with a cautionary note that timings will remain subject to review and a recommendation to all to check latest information on the SCC Highways website before setting out:

Phase 1 – week 1 (w/c 27/03/23 – pre-Easter Holidays/term time) – day works

Phase 2 – week 2 (w/c 03/04/23 – Easter Holidays) – day works

Phase 3 – week 3 (w/c 10/04/23 – Easter Holidays) – day works

Phase 4 – weeks 4, 5 & 6 (w/c 17/04/23, 24/04/23, 01/05/23  – post-Easter Holidays/term time) – night works (plus possible day-works)